Dashboard Upskill Grid Code Compliance for Hyperscale Loads Large Load Interconnection Process Large Load Interconnection Studies — LLIS / RTP / RPG end-to-end

Large Load Interconnection Studies — LLIS / RTP / RPG end-to-end

Three-tier engineering-study sequence governs every large-load interconnection at PJM (Manual M-14H), MISO (BPM-015), ERCOT (§25.494), and CAISO. Tier 1 Feasibility (60-120 d, $50-200 K) — high-level yes/no + cost range. Tier 2 System Impact Study / SIS (6-12 mo, $0.5-2 M) — powerflow under multiple scenarios + N-1 contingencies, dynamic stability for 3φ-fault transients (PSS/E + IEEE Std 1110-2002 models), short-circuit (ASPEN/CAPE) vs breaker ratings, harmonic analysis to IEEE 519 (PSCAD/HARMFLO) when power-electronic loads present. Tier 3 Facilities Study (4-8 mo, $0.5-5 M) — final engineering + binding cost estimate + executed Interconnection Agreement. Cost allocation: direct assignment (100% applicant) vs network upgrade (DFAX) vs postage-stamp (rare). Affected Systems Studies coordinate cross-RTO impacts at major seams (PJM-MISO, MISO-SPP, SPP-WECC, CAISO-WECC); ERCOT exempt. FERC Order 1920 (2024) expands long-term transmission scenario planning. Compliance documents: ISA / LGIA / ERCOT IA + NERC TPL-001-5.1 (P0-P7 contingencies), PRC-024 (V/freq ride-through), PRC-025, IEEE 2800-2022 (IBR standard), MOD-026/027/032 (model data). Violation penalties up to $1 M / day. Total studies → executed agreement: 12-30 mo; construction adds 12-36 mo.

Senior ~16 min

Step 1 - Three study tiers: Feasibility, SIS, Facilities Study

0.55×
step 1/5 topic three tiers ref Feasibility · SIS · Facilities Study

Reference notes

Every large-load interconnection — whether under PJM Manual M-14H, MISO BPM-015, ERCOT §25.494, or CAISO — passes through three progressively detailed engineering studies: Feasibility → System Impact Study (SIS) → Facilities Study. Total time from initial feasibility through executed Interconnection Agreement: 12-30 months. Construction adds another 12-36 months. Use Next → to walk through the three tiers, what each study computes, cost allocation, Affected Systems Studies, and the final compliance documents.

Three study tiers

Tier Duration Cost ($) Output
1. Feasibility60-120 days$50-200 KYes/no feasibility + rough cost range
2. SIS6-12 months$0.5-2 MRequired upgrades list + cost
3. Facilities Study4-8 months$0.5-5 MFinal design + signed Interconnection Agreement

Regional naming: PJM — Feasibility / SIS / Facilities Study · MISO — same with BPM-015 procedures · ERCOT — Pre-screening / Impact Study / Facilities Study under §25.494.

What studies compute

Network upgrades + cost allocation

Affected Systems Studies + FERC seams

Compliance documents

Why it matters for the AWS Grid Code Compliance Manager role

The executed Interconnection Agreement is the foundation. Every operating decision a data center makes for the life of its assets must trace back to commitments in that agreement and the underlying NERC obligations. Annual compliance reviews verify ongoing conformance and identify modifications needed as equipment ages or operating patterns shift. The compliance manager owns this trace — from initial Feasibility filing through 20+ years of operation.